Add automated performance tests using JPT

Description

The Data Center approval process requires that performance tests are executed to determine the impact of the add-on on the system.

The execute of these tests should be automated so its easy to rerun tests when needed.

Environment

None

Activity

Show:

Mark Rekveld March 10, 2019 at 4:08 PM

Performance testing for the Data Center approval process has been outsourced to Move Work Forward.